Concrete is being poured, in relation to curb and gutter. We should see significant progress in relation to the roundabout area with the curb and gutter work so that is exciting.

Grading continues and more grid and stone is being placed to make up for poor soil quality. This means trucks are still coming in with stone, this work is occurring more on the Farm and Fleet side of the road.

Storm sewer continues to go in without any hitches so far. Some electrical work is being done this week as well.

Over all we are still on track and although the grid work has taken a little longer than non grid work would've, the city was aware that this work would need to be done so we are still doing well. Here's hoping for good weather so work can continue!