Weekly Update for the week of August 11th
Grading will continue with the placement if base aggregate. Poor soils have continued as work progresses west causing more work to be done. Geogrid is still being used to reinforce the roadway in poor soil areas. Curb and gutter will continue to go in this week to fill in the gaps that were left for business access. The contractor will be backfilling the curb and gutter that was placed last week so that access sill exists to the businesses. A small portion of asphalt will be placed on Friday. A single lane of paving will start at Parkway and go around the corner at the Mobile and continue a short distance to the north. This is necessary for staging for the round about.
Upcoming
Grading will be completed for the new road bed but more will continue for curb and gutter and sidewalks and drive ways. The rest of the concrete work for the stage one curb and gutter will begin again on Monday August 18th. The concrete curb and gutter will require cure time before it can be backfilled and traffic will be allowed to drive across it. Drive way access will be maintained.
Contact Information
There will be an informal public information session this
Wednesday, July 30 at 6:00 pm. This session is intended to give the public
brief update on the project schedule and address any questions or concerns that
one might have. These meetings will be scheduled every other week.
At any time, please feel free to contact the construction
project leader directly:
Warren Mohar
Cell Phone 608-963-5608
If Warren is not available, after July 31 please call the
assistant project leader:
Ron Voss
Cell Phone 608-963-7416
Thanks Ron! If you have more questions please feel free to comment!