Monday, August 11, 2014

Weekly Update



Weekly Update for the week of August 11th

Grading will continue with the placement if base aggregate. Poor soils have continued as work progresses west causing more work to be done. Geogrid is still being used to reinforce the roadway in poor soil areas. Curb and gutter will continue to go in this week to fill in the gaps that were left for business access. The contractor will be backfilling the curb and gutter that was placed last week so that access sill exists to the businesses. A small portion of asphalt will be placed on Friday. A single lane of paving will start at Parkway and go around the corner at the Mobile and continue a short distance to the north. This is necessary for staging for the round about. 

Upcoming

Grading will be completed for the new road bed but more will continue for curb and gutter and sidewalks and drive ways.  The rest of the concrete work for the stage one curb and gutter will begin again on Monday August 18th. The concrete curb and gutter will require cure time before it can be backfilled and traffic will be allowed to drive across it. Drive way access will be maintained.

Contact Information

There will be an informal public information session this Wednesday, July 30 at 6:00 pm. This session is intended to give the public brief update on the project schedule and address any questions or concerns that one might have. These meetings will be scheduled every other week.

At any time, please feel free to contact the construction project leader directly:
Warren Mohar
Cell Phone 608-963-5608

If Warren is not available, after July 31 please call the assistant project leader:
Ron Voss
Cell Phone 608-963-7416

Thanks Ron! If you have more questions please feel free to comment!