Update for this and next week!
TRAFFIC
Traffic will remain in the one-way configuration utilizing
Lynn Street as the detour route for South Boulevard until early September while
the south half of the roadway is reconstructed.
WORK SCHEDULE FOR THIS WEEK
With the exception of some gaps that were left for
driveway access, the curb and gutter on the south side of the roadway is
completed. Ongoing work includes the installation of concrete sidewalk and
driveways on the south side of the roadway. Sidewalk installation will be the
main focus of the project for the upcoming week.
Once the sidewalk and driveway aprons are poured, the
contractor will place topsoil and sod, and complete any asphalt patching
necessary on driveways and parking lots.
No changes are expected to be made to the traffic control
layout or detour in the upcoming week.
WORK SCHEDULE FOR THE UPCOMING WEEKS
Work will continue on the south side through the first
week in September.
The first lift of asphalt pavement is scheduled to be
placed at that time. Once that first lift of asphalt is placed, traffic will be
shifted to the south side of the roadway and work will begin on stage 2.
CONTACT INFORMATION
There was an informal public information session Wednesday, August 27 at 6:00 pm. This session was intended to give the public
brief update on the project schedule and address any questions or concerns that
one might have. These meetings will be scheduled every other week so plan for one to occur Sept. 10th.
At any time, please feel free to contact the construction
project leader directly:
Warren Mohar
Cell Phone 608-963-5608
Thanks! AW